Emmerson finalises feasibility study components for mine access design and costing
The direct capital cost estimate of mine access components has been estimated at approximately US$34.1 million including a 21.7% contingency.
The direct capital cost estimate of mine access components has been estimated at approximately US$34.1 million including a 21.7% contingency.
Ignacio Salazar will join the Highfield Resources Group as CEO with effect from 20 July 2020.