Itafos restarts sulfuric acid plant at Arraias
The recommissioning of the sulfuric acid plant at Arraias is expected to be completed over a 4-month timeframe in order to commence sulfuric acid sales during 1Q22.
Borefield development progressing at Lake Wells SOP project
A total of 11 new bores have been drilled in the project's western and southern borefields so far, of the 76 new bores scheduled to be developed through project construction.
AUS$740 million project debt funding secured for Mardie SOP project
Total funding of approximately AUS$1.2 billion is required to develop the sulfate of potash (SOP) project to a capacity of 5.35 million tpy of salt and 140 000 tpy of SOP.
KBR inks digital advisory services contract with EuroChem
KBR will proactively analyse operations at EuroChem's Kingisepp ammonia plant.
Fertiglobe, Scatec and Egypt's sovereign fund to develop green ammonia project
The facility will be located near Fertiglobe’s subsidiary EBIC in Ain Sokhna in Egypt and is a first step towards developing a green hydrogen hub in Ain Sokhna.
Incitec Pivot and Fortescue Future Industries to carry out green ammonia study
The study will assess whether industrial-scale manufacturing of green ammonia at the Gibson Island fertilizer manufacturing facility in Queensland, Australia, is technically and commercially feasible on an existing brownfield site.
South Harz Potash signs drilling contract for Ohmgebirge project
The first drillhole, OHM-02, is planned in 4Q21 to a depth of 665 m which is expected to fully penetrate the known potash horizon in the area.
Brazil planning fertilizer project
Speaking during his weekly live broadcast on social media, Brazilian President Jair Bolsonaro did not provide many details on the project but said it would be presented next month.
Trigg Mining publishes scoping study for Lake Throssell SOP project
The study has indicated the project is capable of achieving a nameplate production target of 245 000 tpy of sulfate of potash over an initial Life-of-Mine of 21 years.
Officer Basin potash project given Heritage Clearance for second phase of drilling
The Heritage survey was conducted in accordance with the standards and requirements of Western Desert Lands Aboriginal Corp.