Danakali says EPCM phase 2 of Colluli project in final stage

Published by , Editor
World Fertilizer,


Danakali has announced that the EPCM phase 2 of its Colluli potash project in Eritrea is now in its final stage, with completion anticipated in June 2020.

All vendor and contractor packages have now been received in complete form. The receipt of these bids allows DRA Global (DRA) to finalise the tender evaluation process to provide a technically compliant and commercially favourable estimate.

Three key objectives set for the EPCM phase 2 are:

  • Update of the FEED capital estimate;
  • Revision of the FEED project schedule; and
  • Identification of key test work required to ensure full preparedness for EPCM phase 3.

Completion of the identified test work items provides key data necessary to finalise process plant design development and will allow advancement into EPCM phase 3 with clear direction.

A number of optimisation opportunities to improve project design will be presented at the end of EPCM phase 2.

Read the article online at: https://www.worldfertilizer.com/project-news/21052020/danakali-says-epcm-phase-2-of-colluli-project-in-final-stage/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Fertilizer project news