Acron’s Novgorod site has completed a major overhaul of one of its two step-down substations. Main step-down substation 315 has two 80-MVA transformers and is one of the primary power sources for Acron’s production units.

During the overhaul, old electromechanical protection kits were replaced with new ones that have domestically produced microprocessors. The equipment fees totalled approximately RUB 20 million. Modern digital hardware remotely connects mini-computers to the dispatch system, which integrates them into the computer network.

The overhaul replaced most of the old equipment at step-down substation 315, boosting power supply reliability for NPK production.

According to Acron’s Chief Electrical Technician, Alexei Grigoriev, the overhaul process was unique because it was completed during continuous production using electronic parts produced in Cheboksary.

An overhaul of the second main step-down substation is expected for the near future.