Western Potash agrees binding offtake agreement with Archer Daniels Midland
Published by Nicholas Woodroof,
Editor
World Fertilizer,
Key terms of the offtake agreement include:
- Binding commitment to take 100% of the produced potash from the Phase I project.
- Free-on-board (FOB) mine site and transported from the site by truck to the nearby Port Lajord Terminal, only 13 km from the project site.
- A structure to incentivise the best final sale price for both parties.
In addition, the company is pleased to provide the following updates of the Milestone Phase 1 Project:
Drilling programme
The team has successfully completed drilling of three vertical production wells which intersected high grade potash in all wells, according to the downhole logs. The project has also drilled and connected first injection wells, having achieved on target intersection of the potash bed. This is the first intentionally connected potash well drilled in Saskatchewan, and is a major achievement in the development of the horizontal selective solution mining technique.
Construction
Construction continues to advance in line with the project schedule. Extensive progress has been achieved including construction of building foundations, arrival of equipment and materials, and planning for building construction before the end of the year. The project goal remains to complete Phase I construction in mid 2020 with potash production to commence later next year.
Operations
Operation of the Western Potash water well commenced on 30 August and began filling the crystallisation pond. This water well utilises brackish ground water from approximately 850 m below the surface, which is not suitable for either potable or agricultural use. The pond will be gradually filled over the next three months. The cold mining to saturate the crystallisation pond with salt will commence by October 2019, followed by hot mining of potash in early 2020.
Fritz Venter, President and CEO of Western Potash Corp., commented: “We are very pleased with the progress achieved on the Milestone Project to-date. The offtake agreement for the purchase of our Phase I Project potash with a reputable partner such as ADM gives us great confidence in the final sale of our potash. The recent successful construction, drilling and start of operations to fill the crystal pond proves the project is on track to start production by late 2020. We look forward to the continued safe, on-budget and schedule completion of the project.”
Read the article online at: https://www.worldfertilizer.com/potash/27092019/western-potash-agrees-binding-offtake-agreement-with-archer-daniels-midland/
You might also like
Trammo and Elengy sign MoU for low-carbon ammonia import terminal project in France
The project involves the redevelopment of part of Elengy’s Fos Tonkin LNG terminal site into a low-carbon ammonia import terminal.