K+S report increased potash production at the Werra plant by the end of the year
Published by Robyn Wainwright,
Assistant Editor
World Fertilizer,
Recent rainfall has temporarily raised the water level and flow of the Werra river. Therefore, the disposal situation and the capacity of the retention basin at the Werra potash plant have improved.
The production will only stop from December 24 to 26, and full production will resume at the three sites of the plant from December 27 onwards. K+S previously expected a longer production stoppage.
Due to the production stoppage, which is now shorter than previously assumed, K+S expects only an additional negative EBITDA effect of roughly €10 million (before: maximum of €15 million) in the 4Q18.
K+S assumes further stoppages in the potash production at the Werra plant to be unlikely in the 1Q19, even in the event of drought.
Read the article online at: https://www.worldfertilizer.com/potash/18122018/ks-report-increased-potash-production-at-the-werra-plant-by-the-end-of-the-year/
You might also like
Pivot Bio sustainability programme verifies the avoidance of more than 315 000 t of CO2e since 2022
Pivot Bio has announced that growers opting to validate their implementation of better nitrogen management practices through the company’s N-OVATOR programme have avoided more than 315 000 t of CO2e over the first two years of the programme.