Salt Lake Potash completes civil earthworks for process plant site
Published by Nicholas Woodroof,
Editor
World Fertilizer,
Early process plant construction work has now commenced and the project remains on schedule for December 2020 commissioning. SO4 has implemented plans to minimise potential impact from Covid-19 on its site operations, and has seen no material impact to its suppliers.
Highlights
- Off-lake civil construction earthworks is now complete and contractors and equipment are demobilising. Completed work includes pad preparation for construction of the process plant, power plant, warehouse, workshop, administration and site village, as well as construction of the raw water pond, runoff settlement ponds and site access roads.
- The company has engaged with its suppliers and is not aware of any impact from the Covid-19 shut-down and is planning delivery of all key components as per the project schedule.
- The company expects to be delivering first revenues in 1Q21 and notes that in face of the current economic volatility, SOP markets have remained very resilient with no material changes to the published benchmark indexes.
Tony Swiericzuk, CEO, said: “The current volatile economic environment, and a relatively unchanged SOP price, highlights the resilience of the global agricultural sector. Our Lake Way project continues to rapidly progress and remains on time and on budget with the achievement of another significant milestone.”
Operational update
Following completion of Stage 2 on-lake civils SO4 has now shifted focus to rapid construction of the process plant and non-process infrastructure (accommodation, power, raw water storage, buildings etc.) for the Lake Way project.
At the process plant site, ground clearing and bulk civil earthworks are now complete. This work included pad preparation for construction of the process plant, power plant, warehouse, workshop, administration and site village, as well as construction of the raw water pond, runoff settlement ponds and site access roads. Lake Way Village construction is 60% complete and will be housing workers from mid April 2020.
More than 50% of the long-lead items for the plant and NPI construction have been ordered with engineering and procurement expected to be finalised in coming months.
On-lake the trench network continues to supply aquifer brine to the 400 Ha of solar evaporation ponds that have commenced commissioning as they ramp up to steady state commercial scale operation.
Harvest salts are precipitating as planned and will be used to commission and feed the process plant from late 4Q20.
Covid-19 business update
SO4 has responded with changes to its operations as Government advice regarding Covid-19 has evolved in order to minimise potential impacts. Specifically, interstate workers have elected to transit home while non critical movement to and from site has been minimised. All interaction with the local Wiluna community has ceased. Use of the Wiluna airport for travel to/from site has not been impacted and this airport continues to support the SO4 business.
The company has received no information from suppliers to suggest delays to any items ordered for the process plant and non-process infrastructure.
Read the article online at: https://www.worldfertilizer.com/potash/03042020/salt-lake-potash-completes-civil-earthworks-for-process-plant-site/
You might also like
Vortex Global appoints GNV Enterprise as new representative for Africa
This strategic partnership marks a significant step in Vortex Global’s mission to expand its reach and offer cutting-edge solutions tailored to meet the unique needs of customers across Africa.