AMECO has completed the commissioning of a custom Portal Reclaimer handling 480 tph of urea with a rail span of 54 m for Agrium at Borger Nitrogen Operations facility in Texas.
AMECO designed and supplied a urea storage solution that drags urea from a pile to 20 degrees below ground. This Portal Reclaimer enabled Agrium to increase its storage capacity by 50% more than the standard solution available from other suppliers on the market.
This equipment is the latest example of how AMECO has leveraged its 85 years experience in machine design to deliver a superior product, and best serve its clients’ needs in fertilizer, pulp, biomass, coal power plants and port terminals.
Read the article online at: https://www.worldfertilizer.com/materials-handling/05062017/ameco-completes-portal-reclaimer-commissioning/
You might also like
Ready to revolutionise the cement industry?
Join our sister publication, World Cement, in Lisbon, 10 – 13 March 2024, for their first in-person conference and exhibition: EnviroTech.
This exclusive knowledge and networking event will bring together cement producers, industry leaders, technical experts, analysts, and other stakeholders to discuss the latest technologies, processes, and policies being deployed at the forefront of the cement industry’s efforts to reduce its environmental footprint.
Azomures announce the resumption of fertilizer production
Azomures recently concluded contracts for the purchase of natural gas, which allow the resumption of fertilizer production at 50% of the total capacity of the factory, starting in October 2023.